Delhi HC: Transfer of liabilities from a previous loan agreement makes the arbitration clauses in subsequent agreements, binding

The Division Bench of High Court of Delhi (“Delhi HC”), vide its judgment pronounced on September 13, 2023, in the matter of DD Global Capital Private Limited and Others v. S.E. Investments Limited [FAO (OS) (COMM) 33/2018 and CM APPL. 7434/2018], has dismissed an appeal assailing the impugned judgment dated September 20, 2017 passed by the Single Bench of Delhi HC and held that transfer of liabilities from a previous loan agreement makes the arbitration clauses in subsequent agreements binding.

Facts

DD Global Capital Private Limited (“DD Global/ Appellant No. 1”) approached S.E. Investments Limited (“Respondent”) to avail a loan facility to the tune of INR 4 crores. Pursuant thereto, loan amount of INR 3.20 crores was sanctioned and disbursed in favour of DD Global in July, 2008, which was supposed to be repaid by July 7, 2009 along with interest thereon at the rate of 25% per annum. The aforesaid loan was secured by Appellant Nos. 2 and 3. Also, a piece of land admeasuring around 5.92 acres and situated at Zirakpur, Punjab owned by Renaissance Buildcon Company Private Limited (“RBCL”) was mortgaged in favour of the Respondent to secure the loan disbursed to DD Global. Additionally, RBCL also extended a corporate guarantee in favour of the Respondent towards securing the loan.

However, DD Global failed to repay the loan amount of INR 3.20 crores together with interest. In view thereof, the Respondent agreed to restructure the previous loan. Accordingly, as on July 31, 2010, entire loan amount inclusive of applicable interest was amounting to INR 6.37 crores. There was re-financing of loan on July 31, 2010 by the Respondent to the tune of INR 9.10 crores by way of executing 5 new loan agreements for 1 year duration each at the rate of interest thereon being 30% per annum.

The afore-mentioned re-financed loan agreement was to be repaid within a year and the same was secured by personal guarantees extended by Appellant Nos. 2 and 3, corporate guarantee extended by RBCL and collateral of the mortgaged land belonging to RBCL situated at Zirakpur, Punjab. In addition to the afore-mentioned, the Appellants also executed undertakings/ declaration dated July 31, 2010 and 5 debit vouchers dated July 31, 2010 aggregating to INR 9.10 crores. Also, the Appellants issued post-dated cheques amounting to INR 9.10 crores.

However, in view of default on part of DD Global in repayment of the loan facilities, the Respondent invoked arbitration proceeding as stipulated under Clause 20 of the 5 loan agreements by issuing a common invocation letter dated September 25, 2012. Considering that the aforesaid 5 loan agreements formed part of the same transaction, common arbitration proceeding was initiated by the learned Arbitrator.

Thereafter, the learned Arbitrator passed an award dated June 22, 2016 and held that the Respondent herein is entitled to recover INR 9.10 crores as on July 31, 2010 jointly and severally from Appellants, along with interest for pre-award period and future interest at the rate of 18% per annum.

Pursuant thereto, the Appellants herein approached the Single Bench of Delhi HC seeking to set aside the aforesaid arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”). However, the same was dismissed by the learned Single Judge of Delhi HC vide the impugned order, leading to filing of the present appeal before the Division Bench of Delhi HC by the Appellants.

Issue

Whether an arbitration clause stipulated in the subsequent agreement wherein liabilities stand transferred from the original agreement to a subsequent agreement, will be binding to invoke arbitration proceeding in respect of the original agreement even if the original agreement had no stipulation of arbitration clause.

Arguments

Contentions of the Appellants:

It was submitted that no amounts were disbursed by the Respondent pursuant to loan agreements executed in 2010 and that the Respondent has failed to produce any document to prove the same.

It was further contended that the loan agreements executed in 2008 and 2010 are totally separate and independent from one another. Further, the loan agreement executed in 2008 did not have an arbitration clause and the loan agreements executed in 2010 did not have any reference of the loan agreement executed in 2008. In view thereof, the learned Arbitrator could not have assumed jurisdiction on the matter arising out of loan agreement executed in 2008. Further, arbitration proceedings were invoked only under the aforesaid 5 loan agreements executed on July 31, 2010.

It was further submitted that Appellant had signed blank debit vouchers along with loan agreements executed in 2010. However, as the loan agreements executed in 2010 under which debit vouchers were signed by the Appellants do not make any reference to the loan agreement executed in 2008, as such, debit vouchers could not have been used to repay the monies outstanding under the loan agreement executed in 2008.

Further, the Appellants raised the issue of limitation and contended that claims under the loan agreement executed in 2008 is barred by limitation. The Appellants submitted that the aforesaid contention was raised before the learned Arbitrator as well, however, it was rejected.

Furthermore, the Appellant submitted that in the present case, Respondent had unilaterally appointed the learned Arbitrator. Pursuant to the Arbitration and Conciliation (Amendment) Act, 2015, a party interested in the outcome of arbitration proceeding has no unilateral right to appoint an arbitrator. Notably, the arbitral award in the present case was passed on June 22, 2016, at which point in time, the aforesaid amendment was already introduced. As such, the arbitral award ought to be set aside on this ground alone.

Contentions of the Respondent:

It was submitted on behalf of the Respondent that the arbitral award passed by the learned Arbitrator and the impugned judgment pronounced by the Single Bench of Delhi HC were good in law and need not be set aside.

Observations of the Delhi HC

Delhi HC refused to accept the contention raised by the Appellants that the 5 debit vouchers signed by them were blank and that the 5 loan agreements dated July 31, 2010 are null and void as no amounts were disbursed under the 2010 loan. Delhi HC observed that there is a clear finding by the learned Arbitrator, which has been upheld by the learned Single Judge that the 5 loans agreements dated July 31, 2010 were executed along with other documents as part of re-structuring of the previous loan extended to DD Global on July 3, 2008, which DD Global failed to repay. Consequently, parties had to enter into the aforesaid 5 loan agreements so as to grant a further period up to July 31, 2011. Therefore, such contention raised by the Appellants cannot be accepted.

Delhi HC further observed that the Appellants had admitted to execution of the 5 debit vouchers. In so far as the contention of the Appellants that the debit notes were blank at the time of their execution and were filled up at a subsequent point in time, it was observed that the Appellants have failed to prove the same and there is a clear finding by learned Arbitrator that except for bald statement made by the Appellants, no oral or documentary evidence has been placed on record.

It was further observed that the Appellants did not dispute or challenge the execution and validity of the 5 loan agreements dated July 31, 2010 at any point in time. Further, Delhi HC observed that the learned Arbitrator had rightly held that the 5 debit vouchers dated July 31, 2010 bears reference to adjustment of the original loan availed by DD Global in 2008 and its link to the subsequent loan availed in 2010. Further, it was observed that from the aforesaid debit vouchers, it is clear that the consideration against the 5 loans availed in 2010 was passed on to DD Global by way of adjustment of outstanding dues of the year 2008. The outstanding dues arising out of original loan availed in 2008 were converted into 5 new loans in 2010 and since the aforesaid 5 loan agreements contain an arbitration clause, the present arbitration proceeding was rightly initiated and is maintainable in law.

Further, Delhi HC observed that the learned Single Judge of Delhi HC has arrived at a finding that the conclusion made by the learned Arbitrator, both in terms of facts and law, is a plausible conclusion and there is no reason to disturb the conclusion recorded by the learned Arbitrator. It is a settled law that if the interpretation and conclusion arrived at by the learned Arbitrator is a plausible one, judiciary ought to refrain from disturbing such findings. In this regard, Delhi HC relied upon the judicial pronouncement rendered by the Supreme Court in the matter of MMTC Limited v. Vedanta Limited [(2019) 4 SCC 163], whereby it was held that the court hearing an appeal under Section 37 of the Arbitration Act must be very cautious in disturbing concurrent findings given by the learned Arbitrator and confirmed by the appropriate court in view of challenge under Section 34 of the Arbitration Act.

Further, Delhi HC observed that the contention raised by the Appellants and reliance placed by them on various judgments is highly misplaced in so far as the submission that Respondent had unilaterally appointed the learned Arbitrator. In this regard, Delhi HC observed that the present arbitration proceeding was invoked by letter dated September 25, 2012 whereas the amendment in Arbitration Act was introduced in 2015, whereby a party interested in the outcome of arbitration proceeding has no unilateral right to appoint an Arbitrator. Therefore, the Appellants cannot raise such contention.

Decision of the Delhi HC

Delhi HC held that transfer of liabilities from a previous loan agreement makes the arbitration clauses in subsequent agreements binding. In view of the aforesaid ratio laid down, the Division Bench of Delhi HC was pleased to dismiss the appeal.

VA View:

The present judicial pronouncement rendered by the Division Bench of Delhi HC provides clarity on multiple issues.

The present judgment had laid down the ratio that if liabilities stand transferred from the original agreement to a subsequent agreement, in that case an arbitration clause stipulated in the subsequent agreement will be binding to invoke arbitration proceeding in respect of the original agreement even if the original agreement had no stipulation of arbitration clause.

Further, this judgment clarifies the position on unilateral appointment of learned Arbitrator in view of amendment to the Arbitration Act in the factual context of those cases wherein the arbitration proceeding was invoked prior to the aforesaid amendment in the year 2015.

Lastly, this judgment reiterates the well settled legal position that when the findings arrived at by the learned Arbitrator and if such findings have been confirmed by an appropriate court pursuant to challenge to arbitral award in terms of Section 34 of the Arbitration Act, then the higher judiciary ought to be cautious in disturbing such findings recorded by the learned Arbitrator.

For any query, please write to Mr. Bomi Daruwala at [email protected]

Delhi HC: Claims settled under a resolution plan become non-arbitrable and a reference of those claims would amount to reopening of the resolution plan

The Delhi High Court (“Delhi HC”) has, in its judgement dated October 10, 2023, in the matter of Indian Oil Corporation Limited v. Arcelor Mittal Nippon Steel India Limited [ARB.P. 102/2022], held that claims that have already been settled under a resolution plan would become non-arbitrable once the resolution plan is approved by the committee of creditors (“CoC”) and affirmed by the adjudication authority under the Insolvency and Bankruptcy Code, 2016 (“IBC”).

Facts

Indian Oil Corporation Limited (“Petitioner”) and Essar Steel India Limited (“ESIL”), formerly known as Essar Steel Limited, had entered into a gas supply agreement dated January 15, 2009 (“GSA”). Article 14 of the GSA empowered the Petitioner to call upon ESIL to take remedial steps for payment in the event of ESIL’s failure to lift the entire adjusted annual contract quantity. On May 4, 2016, the Petitioner served a notice on ESIL in pursuance of the ‘take or pay’ obligation enumerated under Article 14 of the GSA for ESIL’s failure to comply with its obligations thereunder. Consequently, ESIL served a termination notice on the Petitioner, which was disputed by the Petitioner on the ground that the Petitioner had not committed any breach of its contractual obligations under the GSA.

Thereafter, the Petitioner issued a demand notice dated April 27, 2017, on ESIL, towards recovery of the payments that were due to it, and upon non-receipt of such payments, the Petitioner subsequently issued a notice of dispute dated May 8, 2017, on ESIL. The Petitioner, in its notice of dispute, called upon ESIL to amicably resolve the dispute as contemplated under the GSA, but, since ESIL failed to respond to such notice, the Petitioner invoked arbitration under the provisions of the GSA.

However, during the pendency of the aforementioned dispute, corporate insolvency resolution process (“CIRP”) was initiated against ESIL and a resolution professional (“RP”) was appointed. While responding to the Petitioner’s notice invoking arbitration, ESIL, in its letter dated August 7, 2017, apprised the Petitioner of the commencement of CIRP and the moratorium as declared by the National Company Law Tribunal, Ahmedabad (“NCLT”). The RP issued public notices inviting claims against ESIL and consequently, the Petitioner filed a claim for INR 3762,58,74,503. However, the RP vide his e-mail dated December 7, 2018, addressed to the Petitioner admitted the Petitioner’s claim for a notional amount of INR 1 to ensure the Petitioner’s participation in the CIRP and clarified that the balance claim amount was not admitted owing to the pending dispute between the Petitioner and ESIL.

The resolution plan submitted by Arcelor Mittal Nippon Steel India Limited (“Respondent”) was approved by the CoC on October 25, 2018 (“Resolution Plan”). NCLT, while according its sanction to the Resolution Plan did not agree with the view of the RP to admit claims of the Petitioner at a notional value of INR 1 and directed the RP to include the claims of operational creditors including the Petitioner in the said Resolution Plan. The RP preferred an appeal before the National Company Law Appellate Tribunal (“NCLAT”) against the decision of the NCLT. However, the NCLAT affirmed NCLT’s view and modified the Resolution Plan to include therein certain claims, such as that of the Petitioner.

Against the order passed by the NCLAT, an appeal was preferred before the Hon’ble Supreme Court (“SC”) in the case of Committee of Creditors of Essar Steel India Limited v. Satish Kumar Gupta and Others [(2020) 8 SCC 531] (“Essar Steel India Case”), wherein the SC set aside the directions of both NCLT and NCLAT in relation to inclusion of claims after the approval of the resolution plan. The SC explained the importance of the clean slate doctrine and held that once a resolution plan has been approved and accepted, the successful resolution applicant cannot be burdened with additional claims by modifying the resolution plan. The SC’s decision affirmed the action of the RP and conferred a seal of finality on the Resolution Plan. Hence, the Respondent, as a successful resolution applicant, acquired 100% shareholding of ESIL and took over its management.

Thereafter, the Petitioner issued a notice of demand, calling upon the Respondent to pay the amounts that were due to the Petitioner under the GSA, however, the Respondent denied any liability arising from the GSA. This led to the Petitioner invoking arbitration against the Respondent, and upon the failure of the Petitioner and the Respondent to mutually appoint an arbitrator, the Petitioner approached the Delhi HC for the appointment of an arbitrator under Section 11 (Appointment of arbitrators) of the Arbitration and Conciliation Act, 1996 (“Act”).

Issues

Whether the approval of the Resolution Plan resulted in an extinguishment of all the claims the Petitioner could enforce against the Respondent.

Whether the approval of the Resolution Plan would render disputes that were sought to be referred for arbitral tribunal’s consideration, as non-arbitrable.

Arguments

Contentions of the Petitioner:

The Petitioner submitted that the admission of claims at a notional amount of INR 1 and the approval of the Resolution Plan could not have been viewed as a conclusive adjudication of the Petitioner’s claims as flowing from the GSA, and therefore the Delhi HC ought to take appropriate steps for the constitution of an arbitral tribunal in order to resolve the dispute between the Petitioner and the Respondent. The Petitioner further contended that the ‘take or pay’ obligations under Article 14 of the GSA were to continue up to the year 2028 and would thus go far beyond the date on which the Resolution Plan was approved by the NCLT. Furthermore, SC’s approval of the Resolution Plan with the Petitioner’s claim being admitted at a notional value of INR 1 could not have been read as depriving the right of the Petitioner to raise claims which otherwise arose out of the GSA.

The Petitioner contended that the GSA was a continuing contract and the liabilities arising therefrom was a cause of action continuing to subsist irrespective of the closure of proceedings under IBC. Thus, the Petitioner was justified in approaching the Delhi HC to exercise the jurisdiction conferred upon the Delhi HC under Section 11 of the Act.

Contentions of the Respondent:

The Respondent contended that the concept of extinguishment of claims would not only have to be considered in the light of the principles laid out by the SC in the Essar Steel India Case but also in light of the express language of the Resolution Plan itself, which provided for the extinguishment and discharge of all liabilities and claims in relation to any corporate guarantees, indemnities and all other forms of credit support provided by ESIL prior to the Resolution Plan approval date, upon the approval of the Resolution Plan.

The Respondent submitted that the SC in Essar Steel India Case had, in unequivocal terms, set aside the judgements of NCLT and NCLAT which had purported to revive the claims of the operational creditors such as the Petitioner, and negate the admission of claims at a notional value of INR 1 by the RP. Therefore, with the approval of Resolution Plan, the adjudication on the claims stood at finality and there could be no further adjudication on those claims. To support its argument, the Respondent relied on the case of Ghanashyam Mishra and Sons Private Limited v. Edelweiss Asset Reconstruction Company Limited [(2021) 9 SCC 657] (“Ghanashyam Mishra Case”), wherein the SC held that “The legislative intent behind this is to freeze all the claims so that the resolution applicant starts on a clean slate and is not flung with any surprise claims. If that is permitted, the very calculations on the basis of which the resolution applicant submits its plans would go haywire and the plan would be unworkable.”

Hence, the referral of the dispute to the arbitral tribunal would amount to a reopening of the Resolution Plan which would not only be wholly impermissible but would also amount to overriding the SC’s pronouncement in the Essar Steel India Case.

The Respondent, bearing in mind the legal position that emerged from the Ghanashyam Mishra Case, concluded its arguments by submitting that the petition filed by the Petitioner under Section 11 of the Act was liable to be dismissed even if one employed the ‘eye of needle’ test, as laid down in the case of NTPC Limited v. SPML Infra Limited [(2023) SCC OnLine 389] (“NTPC Limited Case”), extracts of which have been reproduced below:

“Eye of the Needle: …the pre-referral jurisdiction of the courts under Section 11(6) of the Act is very narrow and inheres two inquiries. The primary inquiry is about the existence and the validity of an arbitration agreement, which also includes an inquiry as to the parties to the agreement and the applicant’s privity to the said agreement…The secondary inquiry that may arise at the reference stage itself is with respect to the non-arbitrability of the dispute. The limited scrutiny, through the eye of the needle, is necessary and compelling. It is intertwined with the duty of the referral court to protect the parties from being forced to arbitrate when the matter is demonstrably non-arbitrable.”

Hence, the claims that were part of the Resolution Plan became non-arbitrable after such plan was approved by the NCLT.

Observations of the Delhi HC

While deciding on the issue on whether the approval of the Resolution Plan resulted in an extinguishment of existing claims, the Delhi HC observed that once a resolution plan is approved by the CoC and the adjudicating authority, it results in the extinguishment of all the existing claims that any party may have against the corporate debtor and no fresh adjudication can take place for any claim that was made part of the resolution plan. Relying on the Ghanashyam Mishra Case, the Delhi HC observed that the underlying theme noticed by the SC in the said case was the recognition of the right of a successful resolution applicant to take over a corporate debtor on a ‘clean’ or ‘fresh slate’, without being burdened by any uncertainties or a specter of irresolution. The approval of a resolution plan is statutorily recognized as a closure to all claims that persons or entities may have against a corporate debtor, and therefore, no fresh claims could be laid or enforced against the successful resolution applicant after the approval of a resolution plan. The Delhi HC observed that the successful resolution applicant cannot be left open to defend or oppose claims which have not been factored in the resolution plan.

The Delhi HC further observed that IBC and the resolution process does not contemplate matters being left inchoate, in fact, it exhorts one to accept the seal of finality and quietude which stands attached to the approval of a resolution plan.

With respect to the question on whether the dispute mentioned in the petition filed by the Petitioner could be said to fall within the ambit of ‘non-arbitrability’, the Delhi HC relied on the NTPC Limited Case where it was observed that a refusal to refer parties to arbitration would be justified when there was ‘not even a vestige of doubt’ with respect to non-arbitrability or where it was evident that the matter was ‘demonstrably non-arbitrable’. Hence, in Delhi HC’s view, once it was accepted that the approval of the Resolution Plan results in the extinguishment of all claims that the Petitioner may have had, the dispute cannot be permitted to be urged again before the arbitral tribunal since it would amount to rewriting upon the clean slate and reopening of the Resolution Plan which would be impermissible in light of the finality accorded by the SC’s decision in the Essar Steel India Case. Moreover, empowering the arbitral tribunal to adjudicate or rule upon such disputes would be contrary to the principles enunciated by the SC in the Ghanashyam Mishra Case.

Decision of the Delhi HC

In view of the entirety of the above, the Delhi HC dismissed the petition filed under Section 11 of the Act and held that once a resolution plan is approved by the CoC and the adjudicating authority, it amounts to extinguishment of all the existing claims that parties may have against the corporate debtor and no fresh claims could be laid or enforced against the successful resolution applicant after the approval of a resolution plan.

Further, the Delhi HC applied the ‘eye of the needle’ test enshrined in the NTPC Limited Case and opined that the disputes mentioned in the petition filed by the Petitioner were non-arbitrable and no reference to the arbitral tribunal was warranted.

VA View:

Through this judgement, the Delhi HC has rightly emphasized on the clean slate doctrine laid down in the Essar Steel India Case wherein the SC held that a successful resolution applicant cannot suddenly be faced with undecided claims after the resolution plan submitted by it has been accepted, as this would amount to a hydra head popping up which would throw into uncertainty, amounts payable by a prospective resolution applicant who would successfully take over the business of the corporate debtor.

The legislative intent of IBC is to enable the successful resolution applicant to take over a corporate debtor on a clean slate and not be burdened by unforeseen liabilities, especially those that are neither factored in nor admitted in the resolution plan. Therefore, once a resolution plan receives assent by the CoC and the adjudicating authority, it results in the extinguishment of all the existing claims that any party may have against the corporate debtor and no fresh adjudication can take place for any claim that was made part of the resolution plan.

For any query, please write to Mr. Bomi Daruwala at [email protected]

Sovereign Wealth Funds in India and Opportunities for Andersen network

SWFs are investment fund engines owned by the Government to achieve pre-determined objectives of the Government. The Government invests through SWFs, inter-alia, to diversify their assets, to secure better gains on their investment, to tap into new jurisdictions, to promote industrialization, etc.

The SWFs investment activities have grown substantially with SWFs having over USD 11.5 trillion in AUM as of February, 20231. In the first 2 (two) decades of the 21st century, the number of SWFs has jumped fivefold from 20 to more than 100 active SWFs2. Over the past decade, the investments by SWFs have increased in the Asian markets owing to wide range of opportunities in the emerging and developing markets.

In India as well, the growth of SWFs investments have been exceptional with SWFs increasing their direct investments in India at USD 6.712 billion in 2022 versus USD 3.797 Billion in 20213. By analysing multiple resources and databases, this paper seeks to give an overview of SWFs, their evolution, investment activities and their regulatory framework in India.

To read the complete article, click Download Newsletter.

Legalaxy – Monthly Newsletter Series – Vol VI – November, 2023

We are pleased to share with you the link to our newsletter “Legalaxy” for November 2023, providing updates on the recent and relevant legal developments in India.

Below are the key highlights of the newsletter:

  • SEBI extends the deadline for complying with enhanced investment adviser qualification by 2 years
  • SEBI revises the manner of achieving minimum public unitholding requirement for InvITs
  • SEBI redefines large corporate and the fund-raising norms in view of ease of doing business
  • SEBI provides limited relaxation under SEBI LODR from sending hard copies of financial statements and proxy forms till September 30, 2024
  • RBI notifies the Master Directions on Non-Banking Financial Company – Scale Based Regulations
  • RBI introduces regulations applicable to Payment Aggregators facilitating cross border payment transactions
  • RBI enumerates on the importance of appointment of 2 whole-time directors
  • Prevention of Money-laundering (Maintenance of Records) Rules, 2005 amended by MoF
  • MCA tweaks rules for dematerialisation of securities under Companies Act – makes it mandatory for private companies
  • MCA tightens the beneficial interest rules under Companies Act – makes it mandatory for every company to designate a person in this regard
  • MCA mandates disclosure of beneficial interest in LLP
  • The wait is over: public companies can now list their securities on permitted foreign stock exchanges
  • MCA provides comfort for shifting of registered office of company from one State/Union Territory to another post resolution under IBC
  • One more step towards ease of doing business – MCA integrated with NSWS for incorporation of companies and LLPs
  • MOEFCC notifies the Battery Waste Management (Amendment) Rules, 2023
  • Ecomark Rules notified by MOEFCC
  • Green Rules notified by MOEFCC
  • MOEFCC notifies the Plastic Waste Management (Second Amendment) Rules, 2023
  • Central Government notifies the establishment of Arbitration Council of India
  • MLJ notifies October 9, 2023, as the effective date for coming into force of certain provisions of The Mediation Act
  • A big relief to the aviation industry from the rigor of Moratorium under IBC
  • MCAFPD notifies the Legal Metrology (Packaged Commodities) Amendment Rules, 2023
  • EPFO releases SOP for management and regulation of exempted establishment under EPF Act

We hope you like our publication. We look forward to your suggestions.

Please feel free to contact us at [email protected]

Supreme Court: No absolute or unfettered discretion on the part of liquidator to cancel an auction which is otherwise valid

The Hon’ble Supreme Court of India (“SC”) has, by its judgment dated September 6, 2023, in the matter of Eva Agro Feeds Private Limited v. Punjab National Bank and Another, held that the mere expectation of the liquidator, that a higher price can be attained, can be no good ground to cancel an otherwise valid auction and go for another round of auction.

Facts

Huvepharma Sea (Pune) Private Limited filed an application against M/s. Amrit Feeds Limited (“Corporate Debtor”) under Section 9 (Application for initiation of corporate insolvency resolution process by operational creditor) of the Insolvency and Bankruptcy Code, 2016 (“Code”). The National Company Law Tribunal, Kolkata Bench (“NCLT”) approved the application, allowing the corporate insolvency resolution process to begin. Eva Agro Feeds Private Limited (“Appellant”) submitted a bid for the subject property of the Corporate Debtor, which included lands measuring total of 105,250.40 sq. ft. (“Subject Property”).

The Appellant who was the successful auction purchaser received an E-auction certificate on July 20, 2021 from the liquidator of the Corporate Debtor (“Respondent No. 2”) certifying that the Appellant had won the auction for the Subject Property. Further, Mr. Vijay Kumar Ghidia, a director and principal shareholder of the Appellant, is also the maternal uncle of Mr. Harish Bagla who is the director of Appellant. He was also an ex-managing director of the Corporate Debtor.

On July 21, 2021, the Appellant received another e-mail from Respondent No. 2 regarding the cancellation of the E-auction certificate dated July 20, 2021 under clause 3(k) of the disclaimer clause of the E-auction – Process Information Document (“E-auction Sale Notice”) thereby informing that the auction of the Subject Property will be done by a fresh E-auction. Aggrieved by the cancellation of the E-auction, the Appellant filed an application with NCLT under Section 60 (Adjudicating Authority for corporate persons) and related provisions of the Code and the Insolvency and Bankruptcy Board of India (Liquidation Process) Regulations, 2016 (“Regulations”). On August 12, 2021, NCLT disposed of the application by directing Respondent No. 2 to send a communication to the Appellant requiring them to deposit the balance sale consideration within the specified time.

The Appellant deposited the balance of consideration money with Respondent No. 2 and received a sale certificate from Respondent No. 2. Pursuant to which Punjab National Bank (“Respondent No. 1”) filed an appeal before the National Company Law Appellate Tribunal, New Delhi (“NCLAT”) under Section 61 (Appeals and Appellate Authority) of Code against the order dated August 12, 2021 passed by the NCLT.

NCLAT, vide its order dated November 20, 2021, set aside the order dated August 12, 2021 passed by the NCLT and gave liberty to Respondent No. 2 to initiate the fresh E-auction process (“Impugned Order”).

Aggrieved by the Impugned Order, the Appellant filed an appeal before the SC under Section 62 (Appeal to Supreme Court) of the Code.

Issues

  • Whether Respondent No. 2 can cancel the E-auction certificate before the completion of the actual sale, without giving proper reasoning.
  • Whether the promoter of the Appellant, who was the co-founder of the Corporate Debtor but resigned a decade ago, can fall within the ambit of a ‘related party’ under the Code.

Arguments

Contentions of the Appellant:

The Appellant submitted that Respondent No. 2 had cancelled the auction sale without giving any proper reasoning or justification, which is arbitrary. The Appellant was the sole and the highest bidder and its bid amount matched the reserve price mentioned in the E-auction Sale Notice. Respondent No. 2 cannot go for a fresh auction keeping the reserve price at the same amount of INR 10 crores which was the bid offered by the Appellant and accepted by Respondent No. 2.

The Appellant further submitted that Respondent No. 1 construed clause 3(k) of the E-auction Sale Notice to suggest that because the full amount had not been paid, it was entitled to use the clause and terminate the offer. Given the entire structure of the Regulations, such a claim is completely implausible. Respondent No. 2 provided no explanation for cancelling the auction procedure.

Further, the promoter of the Appellant retired from the Corporate Debtor in the year 2011 and was no longer connected or associated with the Corporate Debtor or involved in the affairs of the Corporate Debtor and therefore does not fall within the definition of the ‘related party’ as defined under the Code. The Appellant has placed reliance on the judgement of Swiss Ribbons Private Limited and Another v. Union of India and Others, [(2019) 4 SCC 17] in which the court had held that in order to attract disqualification under Section 29A (Persons not eligible to be resolution applicant) of the Code, the relationship must be proximate. Therefore, the Appellant is not disqualified under Section 29A of the Code.

Contentions of the Respondents:

The contention of the Respondent No. 1 was that as per Clause 3(k) of the E-auction Sale Notice, the Respondent No. 2 has the absolute right to accept, reject, adjourn, postpone, or cancel any bids at any stage without assigning any reason. There has been no bar under the Code or the Regulations which restrains the Respondent No. 2 from cancelling an auction sale before the completion of the actual sale.

Respondent No. 2 decided to cancel the E-auction certificate in order to explore the possibility of further price enhancement of Subject Property. It was also submitted by the Respondent No.1 that the promoter of the Appellant was also the founding promoter of the Corporate Debtor so the sale of the Subject Property could not be conducted in favour of a related party of the Corporate Debtor as per Section 29A of the Code.

Observations of SC

SC held that a mere expectation of the Respondent No. 2, that a still higher price may be obtained, can be no good ground to cancel an otherwise valid auction and go for another round of auction. SC observed that as per the provisions of Schedule-I, more particularly paras 1(11) to (13) of the Regulations, a view may be taken that ordinarily the highest bid may be accepted by the Respondent No. 2 unless there are statutory infirmities in the bidding or the bidding is collusive in nature or there is an element of fraud in the bidding process.

Respondent No. 2 must apply his mind to the relevant factors if he does not want to accept the bid of the highest bidder and such application of mind must be visible or manifest in the rejection order itself. SC emphasized the importance and necessity of furnishing reasons while taking a decision affecting the rights of parties, since it is incomprehensible that an administrative authority can take a decision without disclosing the reasons for taking such a decision.

Furthermore, after considering Sections 5(24) (Definitions) and 29A(g) of the Code, SC stated that it is obvious that a person who is a relative of the individual or a relative of the individual’s spouse would be a ‘related party’ in relation to that individual. Aside from that, a ‘related party’ in respect of an individual is a private or public firm in which the individual is a director and possesses more than 2% of its share capital or paid-up share capital with relatives. Furthermore, according to the explanation, both maternal and paternal uncles would fall within the concept of ‘related party’.

While relying on the judgement in Swiss Ribbons Private Limited and Another v. Union of India and Others, [(2019) 4 SCC 17], the SC further held that the terms ‘related party’ and ‘relative’ in the defining sections must be understood in conjunction with the groups of people stated in Explanation I under Section 29A of the Code. As a result, it would only contain those associated with the resolution applicant’s firm. As a result, the term ‘connected person’ would also include someone who manages or controls the Corporate Debtor’s business during the resolution plan’s implementation.

Thus, SC also observed that the disqualification sought to be attached to the Appellant is without any substance as the promoter of the Appellant had ceased to be at the helm of affairs of the Corporate Debtor more than a decade ago and he was not in charge of the Corporate Debtor or an influential member of the Corporate Debtor when the Appellant had made its bid pursuant to the E-auction Sale Notice.

Decision of SC

It was held that NCLAT was not justified in setting aside the order of the NCLT dated August 12, 2021. Consequently, SC set aside the Impugned Order and restored the order of NCLT dated August 12, 2021. The appeal was accordingly allowed.

VA View:

SC has upheld the order of the NCLT and further held that there were no objective materials before the Liquidator to cancel the auction process and to opt for another round of auction.

It is in an administrative framework governed by the rule of law that there can be no absolute or unfettered discretion of the Liquidator to cancel an auction which is otherwise valid. Further, as the Liquidator is vested with a host of duties, functions, and powers to oversee the liquidation process in which he is not to act in any adversarial manner, while ensuring that the auction process is carried out in accordance with law and to the benefit of all the stakeholders. Merely because the Liquidator has the discretion of carrying out multiple auctions, it does not necessarily imply that he would abandon or cancel a valid auction fetching a reasonable price and opt for another round of auction process with the expectation of a better price.

For any query, please write to Mr. Bomi Daruwala at [email protected]

Supreme Court: Admission of claims after the resolution plan has been accepted by CoC would result in making CIRP prolonged and inefficacious

The Supreme Court has, vide its judgement dated September 11, 2023, in the case of RPS Infrastructure Limited v. Mukul Kumar and Another [CA No. 5590/2021], held that the admission of claims after the resolution plan has been accepted by Committee of Creditors (“CoC”) would result in making the Corporate Insolvency Resolution Process (“CIRP”), an endless process.

Facts

M/s. RPS Infrastructure Limited (“Appellant”) entered into an agreement with M/s. KST Infrastructure Private Limited (“Corporate Debtor”) on August 2, 2006, for the purpose of development of land situated at Faridabad, Haryana licensed with the Appellant. However, the Appellant sought arbitration on May 2, 2011, after being aggrieved by the Corporate Debtor’s alleged misconduct pertaining to the advertisement of the project under its own name and without mentioning the name of the Appellant. The arbitral proceedings resulted in an award dated August 8, 2016, in favour of the Appellant. Aggrieved by the award, the Corporate Debtor filed a petition under Section 34 (Application for setting aside arbitral awards) of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”), on September 26, 2016.

The Appellant filed execution proceedings in respect of the said award which was ultimately adjourned sine die on December 22, 2017, due to the pendency of the arbitration proceedings. The arbitration proceedings upheld the award along with some modifications, on April 25, 2019. An appeal was filed against the said order under Section 37 (Appealable orders) of the Arbitration Act which was pending and meanwhile, CIRP was initiated against the Corporate Debtor in respect of its 3 real estate projects by certain homebuyers who had invested in the said projects. The CIRP application was admitted by National Company Law Tribunal, Delhi (“NCLT”) on March 3, 2019. On March 3, 2019, the interim resolution professional (“IRP”) was appointed who invited the claims from the creditors by issuing a public announcement as per Section 15 (Public announcement of corporate insolvency resolution process) of the Insolvency and Bankruptcy Code, 2016 (“IBC”) read with Regulation 6 (Public announcement) of the Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 (“IBBI Regulations”) on March 30, 2019. The IRP was replaced by the CoC on June 18, 2020, and Mr. Mukul Kumar (“Respondent”) was appointed as the resolution professional of the Corporate Debtor.

The resolution plan submitted by KST Whispering Heights Residential Welfare Association was approved by the CoC by a majority vote of 80.74% on July 11, 2020, and was sent to NCLT for approval under Section 31 (Approval of resolution plan) of IBC on September 8, 2020. The Appellant vide an e-mail to Respondent dated August 19, 2020, highlighted their pending claim of INR 35,67,05,337 against the Corporate Debtor arising from the arbitral award which was confirmed with certain modifications during the proceedings under Section 34 of the Arbitration Act. The claim was rejected by the Respondent on August 25, 2020, citing that the time period for submitting the claim was within 90 days from initiation of CIRP and the Appellant was 287 days late and the resolution plan has already been approved by the CoC.

The Appellant filed an application under Section 60(5) (Adjudicating Authority for corporate persons) of IBC before NCLT seeking direction to the Respondent and for admission of its claim. This relief was granted to the Appellant by NCLT vide an order dated November 3, 2020, on the grounds that the claim would have appeared in the Corporate Debtor’s books of accounts and in case such books of accounts were not available, it was the duty of Respondent to obtain them and verify the financial position and it was likely that the Appellant would have missed the public announcement for inviting claims as it was issued through newspapers.

An appeal was filed under Section 61 (Appeals and Appellate Authority) of IBC before the National Company Law Appellate Tribunal, New Delhi (“NCLAT”) against the order of NCLT on the grounds that the potential consequences of allowing such a belated claim would severely affect the CIRP. NCLAT, vide its order dated July 30, 2021 (“Impugned Order”), held that the Respondent had done proper service of inviting claims in accordance with Regulation 6 of IBBI Regulations which only mandates a pronouncement through newspaper. It was also held by the NCLAT that the Appellant failed to show that it filed its claim as soon as it came to know of the initiation of the CIRP. Additionally, if the new claims are entertained, the resolution plan as approved by CoC would be jeopardized.

Aggrieved by the Impugned Order, the Appellant approached the Supreme Court.

Issue

Whether claims can be admitted after the acceptance of the resolution plan by CoC.

Arguments

Contentions of the Appellant:

It was contended by the Appellant that the award was a contingent claim as the proceedings under Section 37 of Arbitration Act was pending before the High Court of Punjab and Haryana. The Appellant also submitted that there ought to be a provision for contingent claims in the resolution plan, as held in the case of State Tax Officer v. Rainbow Papers Limited [Civil Appeal No. 1661 of 2020].

It was also contended by the Appellant that the timeline provided under Section 12 (Time-limit for completion of insolvency resolution process) of IBC is directory in nature. Further, since the resolution plan has not been approved by the Adjudicating Authority, the claim of the Appellant should have been included by the Respondent as a contingent liability.

The Appellant also put forth its lack of awareness as the Corporate Debtor did not disclose the commencement of CIRP, either during the pendency of the proceedings under Section 34 of the Arbitration Act or in the appeal under Section 37 of the Arbitration Act.

Contentions of the Respondent:

It was contended by the Respondent that the Appellant had deemed knowledge of the CIRP since the applicable procedure for inviting claims under IBC and IBBI Regulations were followed.

The Respondent also contended that the floodgates of litigation would be opened if the Appellant’s belated claim was allowed. In order to substantiate its argument, the Respondent relied on the case of Committee of Creditors of Essar Steel India Limited through Authorised Signatory v. Satish Kumar Gupta and Others, [Civil Appeal No. 8766-67 of 2019], wherein it was held by the Supreme Court that a successful resolution applicant cannot be faced with undecided claims after the resolution plan has been accepted.

It was urged by the Respondent that no arrangement for contingent claims should be made as the preparation of the resolution plan has been done in line with the information memorandum which is comprehensive and takes due care of the claims of the homebuyers.

Observations of the Supreme Court

The Supreme Court observed that there was no fault on the part of the Respondent except that the Respondent should have made effort to locate the liabilities pertaining to the said award from the records of the Corporate Debtor.

As the Corporate Debtor is a commercial entity, it was also observed by the Supreme Court that the pendency of litigation against the Corporate Debtor is an undoubtable fact. Therefore, the Appellant should have been vigilant to identify if the Corporate Debtor was undergoing CIRP.

The Respondent did the needful what could be done to procure the Corporate Debtor’s records and even moved an application under Section 19 of IBC. A public announcement of CIRP through newspaper is mandated under Section 15 of IBC and Regulation 6 of the IBBI Regulations and it would result in constituting deemed knowledge of the Appellant. Therefore, the plea of not being aware of newspaper pronouncements does not stand valid.

Decision of the Supreme Court

In view of the entirety of the above, it was held by the Supreme Court that after the acceptance of the resolution plan, the fresh claim cannot be admitted and the hydra-headed monster of undecided claims cannot be unleashed on the resolution applicant.

VA View:

CIRP is a time-bound process which may be extended in certain circumstances and varies from case-to-case based on the different facts and circumstances of the case. In the present case, the claim filed by the Appellant was 287 days late which depicts the lapses on the part of the Appellant.

This judgement has led to the establishment of a much-needed precedent which contemplates that no admission of claims should take place once the resolution plan has been accepted by CoC as admission of further claims would make the CIRP perpetual. This judgment makes it clear that the potential consequences of allowing such a belated claim after the approval of the resolution plan by the CoC would set the clock back on the CIRP and thus making the entire CIRP, never ending and inefficacious.

For any query, please write to Mr. Bomi Daruwala at [email protected]