Between the Lines | Supreme Court: Application to initiate corporate insolvency resolution process will be rejected so long as a dispute truly exists in fact and is not spurious, hypothetical or illusory

The Supreme Court (“SC”) has, by an order passed in the matter of Kay Bouvet Engineering Limited v. Overseas Infrastructure Alliance (India) Private Limited [Civil Appeal No. 1137 of 2019], decided on August 10, 2021 (“Judgement”), upheld the order passed by the National Company Law Tribunal (“NCLT”) on July 26, 2018, wherein the SC concluded that the application for corporate insolvency resolution process will be rejected so long as a dispute truly exists in fact and is not spurious, hypothetical or illusory.

Facts
The instant case was an appeal filed by Kay Bouvet Engineering Limited (“Appellant”), before the SC, challenging the order dated December 21, 2018, passed by the National Company Law Appellate Tribunal (“NCLAT”). The NCLAT had set aside the order passed by the NCLT, by which the NCLT had rejected the application filed by Overseas Infrastructure (Alliance) Private Limited (“Respondent”) as an operational creditor under Section 9 (Application for initiation of corporate insolvency resolution process by operational creditor) of the Insolvency and Bankruptcy Code, 2016 (“IBC”) for seeking initiation of corporate insolvency resolution process (“CIRP”) against the Appellant. The NCLAT remitted the matter to the NCLT with a direction to admit the petition filed by the Respondent under Section 9 of the IBC after serving demand notice to the Appellant so as to enable it to settle the claim.

The Government of India (“GoI”) had extended a dollar line credit of USD 150 Million to the Republic of Sudan through Exim Bank of India for carrying out Mashkour Sugar Project in Sudan. On October 11, 2009, Mashkour Sugar Company, Sudan (“Mashkour”), entered into a contract with the Respondent, as per which Mashkour was to nominate a sub-contractor. Subsequently, the Appellant was appointed as a sub-contractor through a tripartite agreement, for executing the whole work of designing, engineering, supply, installation, erection, testing and completion of factory plant for Mashkour for a consideration of USD 106.200 million. For the first tranche of payment, the Respondent transferred an amount of INR 47.12 crores (equivalent to USD 10.62 Million) to the Appellant.

Pursuant to exchange of communications between Ministry of External Affairs, GoI and the Sudan Government, the Ambassador of Sudan to India advised GoI to terminate the contract of Mashkour with the Respondent and to appoint the Appellant as the contractor. However, the contract with the Respondent was terminated by Mashkour for failure on its part to perform the duties.

The Respondent served a demand notice to the Appellant under Section 8 (Insolvency resolution by operational creditor) of the IBC alleging default under the tripartite agreement, claiming the amount of USD 10.62 Million paid by the Respondent to the Appellant. The Appellant denied the claim of the Respondent, specifying that the amount was received from Mashkour and only routed through the Respondent and the same stood adjusted under the new agreement.

The Respondent filed an application for initiation of CIRP against the Appellant as an operational creditor. However, the NCLT dismissed the petition. Aggrieved, the Respondent herein, filed an appeal with the NCLAT, wherein NCLAT set aside the order of NCLT. The instant case is an appeal against the order of the NCLAT, filed by the Appellant.

Issue
Whether the allegation of the Appellant with regard to the existence of dispute can be considered to be spurious, illusory or not supported by any evidence.

Arguments
Contentions raised by the Appellant:
By no stretch of imagination, the claim made by the Respondent could be considered to be an operational debt and as such, the Respondent would not fall under the definition of an operational creditor, enabling it to invoke the jurisdiction of the NCLT under Section 9 of the IBC. It was further submitted that, no amount was receivable by the Respondent from the Appellant in respect of the provisions of goods or services, including employment or a debt in respect of the payment of dues.Hence, the said claimed amount would not be covered under the definition of operational debt as provided under Section 5 (21) of the IBC.

It was argued that the payment, which was made to the Appellant by the Respondent, was from the amount received by the Respondent from Mashkour and only routed through the Respondent and the same stood adjusted under the new agreement.

The demand notice and reply thereto, clarified that there was an “existence of dispute” and hence the NCLT had rightly dismissed the petition. However, the NCLAT, misconstruing the provisions, allowed the appeal and directed the admission of the petition under Section 9 of the IBC.

Contentions raised by the Respondent:
The amount which was paid to the Appellant, was an amount paid from the funds of the Respondent and not from Mashkour. It was submitted that a perusal of material placed on record would reveal that the Appellant had admitted receiving the amount from the Respondent and once the party admits of any claim, the same would come in the definition of operational debt as defined under Section 5(21) of the IBC and enable the party to whom admission is made to file the proceedings under Section 9 of the IBC being an operational creditor. Thus, the NCLAT had rightly considered the provisions and allowed the appeal of the Respondent directing the admission of the petition under Section 9 of the IBC. Therefore, it was submitted that the instant appeal deserved to be dismissed.

Observations of the Supreme Court
The SC noted that an operational creditor, on the occurrence of default, is required to deliver a demand notice of unpaid operational debt or a copy of invoice, demanding payment of the amount involved in the default to the corporate debtor. Within ten days of the receipt of such demand notice or copy of invoice, the corporate debtor is required to either bring to the notice of the operational creditor, the existence of a dispute or to make the payment of unpaid operational debt. Thereafter, as per Section 9 of the IBC, after the expiry of the period of ten days from the date of delivery of notice or invoice demanding payment under Section 8(1) of the IBC, if the operational creditor does not receive payment from the corporate debtor or notice of the dispute under Section 8(2) of the IBC, the operational creditor is entitled to file an application before the NCLT for initiating the CIRP.

The SC noted that in the judgement of Mobilox Innovations Private Limited v. Kirusa Software Private Limited [(2018) 1 SCC 353], it was observed that one of the objects of the IBC qua operational debts is to ensure that the amount of such debts, which is usually smaller than that of financial debts, does not enable operational creditors to put the corporate debtor into the CIRP prematurely or initiate the process for extraneous considerations, therefore, it is enough that a dispute exists between the parties.

The SC also explained the scope of the statutory phrase “existence of a dispute” and the role of the NCLT when adjudicating the same under Section 8(2)(a) of the IBC. The SC opined that, once the operational creditor had filed an application which was otherwise complete, the NCLT was required to reject the application under Section 9(5)(ii)(d) of the IBC, if a notice of dispute had been received by operational creditor or if there was a record of dispute in the information utility. The SC noted that, notice by the corporate debtor must intimate the operational creditor about the existence of a dispute or of the pendency of a suit or arbitration proceedings relating to a dispute between the parties.

The SC noted that all that the NCLT was required to see was whether there was a plausible contention which required further investigation and determine that the dispute was not a patently feeble legal argument or an assertion of fact unsupported by evidence, and not whether the defence is likely to succeed or not.

The SC observed that the Appellant had pressed into service the “existence of dispute” for opposing the demand made by the Respondent. Examining whether the dispute raised by the Appellant can be considered as spurious, illusory and unsupported by evidence, the SC noted that the contention of the Appellant that the amount of INR 47.12 crores, which was paid to the Appellant by Respondent, was paid on behalf of Mashkour from the funds released to Respondent on behalf of Mashkour, cannot be said to be a dispute which was spurious, illusory or not supported by the evidence placed on record. Moreover, the SC affirmed that the initial payment which was made to the Appellant as a sub-contractor by the Respondent, who was a contractor, was made on behalf of Mashkour and from the funds received by the Respondent from Mashkour.

The SC agreed with the view taken in Mobilox (supra) and thus concluded that so long as a dispute truly existed in fact and was not spurious, hypothetical or illusory, the adjudicating authority had no other option but to reject the application.

Decision of the Supreme Court
The SC upheld the decision of the NCLT and stated that it had rightly rejected the application of the Respondent on grounds that there existed a dispute, raised by the Appellant. The SC held that the NCLAT had patently misinterpreted the factual as well as the legal position and had erred in reversing the order of the NCLT. Thus, the SC quashed the order passed by the NCLAT.

VA View:
The SC by this Judgement, has elaborated on the statutory phrase “existence of dispute” and affirmed the view that a genuine dispute must be bona fide and must truly exist in fact, and the grounds for dispute must not be spurious, hypothetical, illusory or misconceived. The defense of “existence of dispute” must be carefully examined and a conclusion as to whether it truly exists in fact should be determined before an application for CIRP is admitted. The SC upheld the legislative intent, which was to prevent premature initiation of CIRP against the corporate debtor.

Further, the SC clarified the limited scope of the adjudicating authority, which was restricted to merely determining whether the dispute was a patently feeble legal argument or not. Emphasizing on the importance of separating the grain from the chaff, so as to reject a spurious defense, which was a mere bluster, the SC, by this Judgement, threw light on the necessity to ascertain that there exists a claim with some substance, rather than it being frivolous and vexatious.

For more information please write to Mr. Bomi Daruwala at [email protected]

 

Between the Lines | Supreme Court: An emergency award passed under the SIAC rules can be enforced in India under Section 17 of the Arbitration Act.

The Hon’ble Supreme Court (“SC”) has in its judgment dated August 06, 2021 (“Judgement”), in the matter of Amazon.com NV Investment Holdings LLC v. Future Retail Limited & Others [Civil Appeal No.4492-4493/2021], held that, the emergency award passed under the arbitration rules of Singapore International Arbitration Centre (“SIAC Rules”) can be enforced in India under Section 17 (Interim measures ordered by arbitral tribunal) of the Arbitration and Conciliation Act, 1996 (“Act”).

Facts
Mr. V.K. Rajah, who was appointed as per the SIAC Rules (“Emergency Arbitrator”) passed an emergency award dated October 25, 2020 (“Emergency Award”) in an arbitration proceeding commenced by Amazon.com NV Investment Holdings LLC (“Amazon / Appellant”) against Future Retail Limited, respondent no. 1, India’s second-largest offline retailer (“FRL”), Future Coupons Private Limited, respondent no. 2, a company that holds 9.82% shareholding in FRL and is controlled and majority-owned by respondent nos. 3 to 11 (“FCPL”) and respondent nos. 1 to 13 (respondent nos. 1 to 13 are hereinafter collectively referred to as the “Biyani Group/Respondents”). The seat of the arbitral proceedings was New Delhi, and the applicable rules were SIAC Rules.

Earlier, a shareholders’ agreement dated August 12, 2019, was entered into amongst the Biyani Group, (“FRL SHA”), wherein, FCPL was accorded negative, protective, special, and material rights with regard to FRL including, in particular, FRL’s retail stores (“Retail Assets”). The rights granted to FCPL under FRL SHA were to be exercised for Amazon’s benefit and thus were mirrored in a shareholders’ agreement dated August, 22, 2019 entered into between Amazon, FCPL, and respondent nos. 3 to 13 (“FCPL SHA”). Consequently, on December 26, 2019, Amazon invested a sum of INR 1,431 crores in FCPL (“Investment”) based on the rights granted to FCPL under both the FRL SHA and the FCPL SHA. It was expressly stipulated that the Investment in FCPL would “flow down” to FRL. The Investment had been recorded in the share subscription agreement dated August 22, 2019 entered into between Amazon, FCPL, and respondent nos. 3 to 13.

The basic understanding between the parties was that Amazon’s Investment in the Retail Assets of FRL would continue to vest in FRL, as a result of which, FRL could not transfer its Retail Assets without FCPL’s consent, which, in turn, could not be granted unless Amazon had provided its consent. Also, FRL was prohibited from encumbering / transferring / selling / divesting / disposing of its Retail Assets to “restricted persons”, being prohibited entities, with whom the Biyani Group could not deal. The Mukesh Ambani group (“Reliance Industries Group”) was a “restricted person” under both the FRL SHA and the FCPL SHA. However, on August 29, 2020, Biyani Group entered into a transaction with the Reliance Industries Group which envisaged the amalgamation and consequential cessation of FRL as an entity, and the complete disposal of the Retail Assets in favour of the Reliance Industries Group (“Transaction”). Therefore, Amazon initiated arbitration proceedings and sought for an emergency interim relief (injunctions) under the SIAC Rules, against the Transaction which was granted by way of the Emergency Award.

Thereafter, Biyani Group still proceeded with the Transaction, and described the Emergency Award as a nullity and the Emergency Arbitrator as coram non judice in order to press forward for permissions before statutory authorities/regulatory bodies. However, FRL filed a civil suit before the Delhi High Court (“DHC”), wherein it sought to interdict the arbitration proceedings and sought for an interim relief to restrain Amazon from writing to statutory authorities by relying on the Emergency Award, calling it a “tortious interference” with its civil rights. The DHC by its order dated December 21, 2020, refused to grant any interim injunction because there may not be irreparable loss to FRL since, it will be for the statutory authorities/regulators to apply their mind to the facts and legal issues therein and come to the right conclusion. An appeal had been filed by Amazon (currently pending before the SC) against certain observations made in this order.

Meanwhile, Amazon filed an application under Section 17(2) of the Act to enforce the Emergency Award which was disposed of on February 02, 2021, by the learned single judge of DHC, who passed a status-quo order wherein he restrained the Biyani Group from proceeding with the Transaction (“Order”). An appeal against the Order was filed by FRL, in which a division bench, after reaching certain prima facie findings, by order dated February 08, 2021, stayed the operation, implementation, and execution of the Order. Again, division bench of the DHC by order dated March 22, 2021 (“Impugned Orders”) referred to its aforementioned order and extended the stay of the Order till April 30, 2021 (the next date of hearing). ‘Special Leave Petitions’ were filed before the SC against the Impugned Orders.

On March 18, 2021, the learned single judge passed a detailed judgment giving reasons for an order made under Section 17(2) read with Rule 2-A (Consequence of disobedience or breach of injunction) of Order XXXIX (Temporary Injunctions and Interlocutory Orders) of the Code of Civil Procedure, 1908 (“CPC”) in which it was held that an Emergency Award was enforceable as an order under Section 17(1) of the Act. Since breaches of the agreements aforementioned were admitted, it further held that the injunctions/directions granted by the Emergency Award were deliberately flouted by the Biyani Group. He further observed that any so-called violations of the Foreign Exchange Management Act, 1999, did not render the Emergency Award a nullity, and, therefore, issued a show-cause notice under Rule 2-A of Order XXXIX of the CPC, after imposing INR 20 lakh as costs. The matter was listed for further directions on April 28, 2021. Against the said judgment, an appeal was filed by FRL before the SC.

The SC stayed further proceedings before the learned single judge as well as the division bench of the DHC, and set the matter down for final disposal before the SC by its order dated April 19, 2021.

Issues
i. Whether the Emergency Arbitrator’s award is contemplated under the Act; and
ii. Whether the Emergency Award can be enforced in India under Section 17 of the Act.

Arguments
Contentions raised by the Appellant:
The order dated February 08, 2021, referred to an agreement between FRL and Reliance Retail Limited, which is an error apparent on the face of the record. The Order and the Impugned Orders of the Division Bench of the DHC suffered from a complete non-application of mind. Further, the Act reflects the grundnorm of arbitration as being party autonomy. The Act is a complete code in itself and if an appeal does not fall within the four corners of Section 37(Appealable orders) of the Act, then the appeal is incompetent. A non-obstante clause was added to Section 37(1) of the Act, thereby making it abundantly clear that no appeal could possibly be filed if it was outside the four corners of Section 37 of the Act. The Emergency Award must be taken as it stands as no appeal was made therefrom by the Biyani Group and, therefore, it was not permissible to go behind the Emergency Award. The non-signatories to arbitration agreements would nevertheless be bound thereby and on facts, it was admitted that the “Ultimate Controlling Person” behind the entire transaction was Mr. Kishore Biyani, who was defined as such under the 3 agreements. After openly flouting the Emergency Award, they would have no case on merits to resist the directions issued by the learned single judge, DHC under Section 17(2) of the Act.

Contentions raised by the Respondents:
The 246th Law Commission Report was referred, in which the amendment of Section 2 of the Act was proposed, to include within Section 2(1)(d) of the Act, a provision for the appointment of an emergency arbitrator. However, the parliament did not adopt the same when it amended the Act by the Arbitration and Conciliation (Amendment) Act, 2015 (“2015 Amendment Act”). Thereby, given the scheme of the Act, an arbitral tribunal as defined by Section 2(1)(d) of the Act can only mean a tribunal that is constituted between the parties, which then decides the disputes between the parties finally and cannot include the Emergency Arbitrator who is not an “arbitral tribunal” but a person who only decides, an interim dispute between the parties which never culminates in a final award. The scheme, therefore, of the entirety of Part I of the Act, would show that the Emergency Arbitrator is a foreigner to the Act and cannot fit within its scheme unless an amendment is made by parliament.

The provisions of the SIAC Rules relating to an emergency arbitrator’s award, which were agreed to between the parties, were subject to the provisions of the Act. Since the Act did not provide for emergency arbitrators, this part of the SIAC Rules would not apply, making it clear that the Emergency Arbitrator’s award cannot fall within Section 17(1) of the Act. The scheme of Section 17(1) of the Act made it clear that a party may, during arbitral proceedings, apply to the arbitral tribunal. However, under the SIAC Rules, the Emergency Arbitrator was appointed before the arbitral tribunal is constituted. This being the case, the Emergency Arbitrator, not being appointed during arbitral proceedings, fell outside Section 17(1) of the Act.

Observations of the Supreme Court
Party Autonomy:
The SC, on reading of the provisions of the Act, noted that, an arbitration proceeding can be administered by a permanent arbitral institution. Further, Section 2(6) (construction of references) of the Act clarified that parties were free to authorise any person including an institution to determine issues that arose between the parties. Also, under Section 2(8) of the Act, party autonomy went to the extent of an agreement which included being governed by SIAC Rules referred to in the FRL SHA and the FCPL SHA. Likewise, under Section 19(2) of the Act, parties were free to agree on the procedure to be followed by an arbitral tribunal in conducting its proceedings. The SC noted that, importance of party autonomy being virtually the backbone of arbitrations was delineated in the judgment of Centrotrade Minerals & Metal Inc. v. Hindustan Copper Limited [(2017) 2 SCC 228]. Further, the SC noted that, the instant case was akin to Centrotrade (supra), that, the parties to the contract, in the present case, by agreeing to the SIAC Rules and the award of the Emergency Arbitrator, had not bypassed any mandatory provision of the Act. There is nothing in the Act that prohibits contracting parties from agreeing to a provision providing for an award being made by an Emergency Arbitrator. The SC observed that, on the contrary, various provisions of the Act provide for party autonomy in choosing to be governed by institutional rules, hence it was clear that the SIAC Rules would apply to govern the rights between the parties, as specifically endorsed by the Act.

Scope of Arbitral Proceedings & Arbitral Tribunal:
The SC further noted that, Section 21 (Commencement of arbitral proceedings) of the Act, subject to agreement by the parties, provided that arbitral proceedings in respect of a particular dispute commenced on the date on which a request for that dispute to be referred to arbitration is received by the respondent. The SC noted that, under rule 3.3 of the SIAC Rules, the arbitral proceedings commenced from the date of receipt of a complete notice of arbitration by the ‘Registrar of the SIAC’. Therefore, the SC observed that, the arbitral proceedings under the SIAC Rules commence much before the constitution of an arbitral tribunal thereunder. The SC observed that, when Section 17(1) of the Act uses the expression “during the arbitral proceedings”, the said expression would be elastic enough, when read with the provisions of Section 21 of the Act, to include emergency arbitration proceedings, which commence after receipt of notice of arbitration by the ‘Registrar’ under Rule 3.3 of the SIAC Rules. The SC observed that, a conjoint reading of these provisions coupled with there being no interdict, either express or implied, against the Emergency Arbitrator would show that the Emergency Award, provided for under SIAC Rules, would be covered by the Act.

The SC also analysed the issue – whether the definition of “arbitral tribunal” under Section 2(1)(d) of the Act should so constrict Section 17(1) of the Act, making it apply only to an arbitral tribunal that can give final reliefs by way of an interim or final award. The SC noted that, the “arbitral tribunal” as defined in Section 2(1)(d) of the Act speaks only of an arbitral tribunal that is constituted between the parties and which can give interim and final relief, “given the scheme of the Act”. However, like every other definition section, the definition contained in Section 2(1)(d) of the Act only applies “unless the context otherwise requires”. The SC observed that given that the definition of “arbitration” in Section 2(1)(a) of the Act meant any arbitration, whether or not administered by a permanent arbitral institution, when read with Sections 2(6) and 2(8) of the Act, would clarify that, even interim order that is passed by Emergency Arbitrator under the SIAC Rules would, on a proper reading of Section 17(1) of the Act, be included within its ambit. The SC observed that, it is significant to note the words “arbitral proceedings” are not limited by any definition and thus encompass proceedings before the Emergency Arbitrator.

Section 17(1) of the Act provides for the application by a party for interim reliefs. There is nothing in Section 17(1) of the Act, when read with the other provisions of the Act, to interdict the application of rules of arbitral institutions that the parties may have agreed to. Therefore, insofar as Section 17(1) of the Act is concerned, the “arbitral tribunal” would, when institutional rules apply, include an emergency arbitrator, the context of Section 17 of the Act “otherwise requiring”, that is, the context being interim measures that are ordered by arbitrators. The same object and context would apply even to Section 9(3) of the Act which clarifies that the court shall not entertain an application for interim relief once an arbitral tribunal is constituted unless the court finds that circumstances exist which may not render the remedy provided under Section 17 of the Act efficacious. Since Sections 9(3) and 17 of the Act form part of one scheme, it is clear that the arbitral tribunal spoken of in Sections 9(3) and 17(1) of the Act would include the Emergency Arbitrator appointed under SIAC Rules. The SC observed that, therefore, even if Section 25.2 of the FCPL SHA (pari materia with Section 15.2 of the FRL SHA) made the SIAC Rules subject to the Act, the said Act, properly construed, would include Emergency Award, there being nothing inconsistent in the SIAC Rules when read with the Act.

The SC noted that, Rule 1.3 of the SIAC Rules indicated that an award of Emergency Arbitrator was included within the ambit of the SIAC Rules. The SC observed that “arbitration” mentioned in Section 25.2 of the FCPL SHA would include an arbitrator appointed in accordance with the SIAC Rules which, in turn, would include the Emergency Arbitrator. The SC noted that as per the SIAC Rules the Emergency Arbitrator had all the powers vested in an arbitral tribunal, including the authority to rule on his own jurisdiction. Further that, the Emergency Award issued by the Emergency Arbitrator which was exactly like an order of an arbitral tribunal, would continue to bind the parties unless the tribunal is not constituted within 90 days of such order or award or it is modified or vacated by the arbitral tribunal, once it is constituted, or until the tribunal makes a final award or until the claim is withdrawn.

Interpretation and objective of various provisions of the Act:
The SC noted that, the 246th Law Commission Report did provide for the insertion of an emergency arbitrator’s orders into Section 2(1)(d) of the Act with an objective to ensure that institutional rules such as the SIAC Rules are given statutory recognition in India. The SC noted that, in the case of Avitel Post Studioz Limited and Others v. HSBC PI Holdings (Mauritius) Limited [(2021) 4 SCC 713], it was held that, mere fact that a recommendation of a ‘Law Commission Report’ was not followed by Parliament, would not necessarily lead to the conclusion that what has been suggested by the Law Commission cannot form part of the statute as properly interpreted. The SC noted that, the 246th Law Commission Report also recommended the insertion of Section 9(2) with an objective to ensure the timely initiation of arbitration proceedings by a party who is granted an interim measure of protection and 9(3) with an objective to reduce the role of the courts in relation to grant of interim measures once the arbitral tribunal has been constituted in alignment with the spirit of the UNCITRAL Model Law as amended in 2006. The 2015 Amendment Act, therefore, introduced sub-sections (2) and (3) to Section 9, the SC observed that, in essence, what is provided by the SIAC Rules, is reflected in Sections 9(2) and 9(3) so far as interim orders passed by courts are concerned. Accordingly, Section 17 of the Act was substituted by the 2015 Amendment Act to provide the arbitral tribunal the same powers as a court would have under Section 9 to provide for interim relief. Also, Section 17(2) of the Act was added so as to provide for enforceability of such orders, again, as if they were orders passed by a court, thereby bringing Sections 17(Interim measures ordered by arbitral tribunal) on par with 9(Interim measures by court) of the Act.

The DHC judgment in Raffles Design International India Private Limited v. Educomp Professional Education Limited, [2016 SCC OnLine Del 5521] dealt with an award by an Emergency Arbitrator in an arbitration seated outside India (as was mentioned in Srikrishna Committee Report (“SCR”)). The SCR laid down that it is possible to interpret Section 17(2) of the Act to enforce emergency awards for arbitrations seated in India, and recommended that the Act be amended only so that it comes in line with international practice in favour of recognising and enforcing an emergency award and Section 9(3) of the Act would show that the objective was to avoid courts being flooded with Section 9 petitions when an arbitral tribunal is constituted for two good reasons – (i) that the clogged court system ought to be decongested, and (ii) that an arbitral tribunal, once constituted, would be able to grant interim relief in a timely and efficacious manner.

An Emergency Arbitrator’s “award”, would undoubtedly be an order which furthers the above mentioned objectives. Given the fact that party autonomy is respected by the Act and that there is otherwise no interdict against the Emergency Arbitrator being appointed, it was clarified that the Emergency Award would fall within the institutional rules to which the parties have agreed, and would consequently be covered by Section 17(1) of the Act, when read with the other provisions of the Act. The SC observed that a party cannot be heard to say, after it participates in an emergency award proceeding, having agreed to institutional rules made in that regard, after losing, turn around and say that the award is a nullity or coram non judice. The SC noted that, having agreed to be governed by the SIAC Rules, Biyani Group cannot ignore the Emergency Arbitrator’s award by stating that it is a nullity when such party expressly agreed to the binding nature of it.

Decision of the Supreme Court
The SC answered the issues in affirmative, by declaring that full party autonomy is given by the Act to have a dispute decided in accordance with institutional rules which can include emergency arbitrators delivering interim orders, described as “awards”. The SC observed that, Section 17 of the Act, as construed in the light of the other provisions of the Act, clearly leads to the position that Emergency Award is recognised under the provisions of Section 17(1) of the Act and can be enforced under the provisions of Section 17(2) of the Act.

VA View:
The SC in this Judgement correctly observed that the Act is a statute which favours the remedy of arbitration so as to provide expeditious interim reliefs to the parties and declog civil courts which are, in today’s milieu, extremely burdened. The SC veraciously observed that, no order bears the stamp of invalidity on its forehead and has to be set aside in regular court proceedings as being illegal. Even if, subsequently, an order is set aside as having being passed without jurisdiction, for the period of its subsistence, it is an order that must be obeyed. Therefore, the Biyani Group was supposed to act in accordance with the Emergency Award.

Party autonomy is the fulcrum in arbitration agreements and Amazon had exercised its choice of forum for interim relief specified thereunder. Thereby, the SC opined that nothing in the Act prohibited contracting parties from obtaining relief from the Emergency Arbitrator. Hence, in such a case where parties had expressly chosen SIAC Rules as the curial law governing the conduct of arbitration, the court would look at the SIAC Rules to the extent that the same was not contrary to the public policy or the mandatory requirements of the law of the country in which arbitration was held. The provisions of emergency arbitration under the SIAC Rules are not contrary to any mandatory provisions of the Act. Hence, the Emergency Arbitrator prima facie was not a coram non judice and the Emergency Award was not invalid.

For more information please write to Mr. Bomi Daruwala at [email protected]

GST Cafe | Refund of unutilized credit accumulated on account of inverted duty structure for tax paid on input services cannot be claimed: SC

We are pleased to share with you the copy of our latest GST Café, which is a briefing on the judgment of the Hon’ble Supreme Court of India in Union of India V VKC Footsteps, where the refund of unutilized input tax credit on account of the rate of input services being higher than outward supplies, cannot be claimed.

To read the GST Cafe, click at the Download Newsletter.

We trust that you will find the same useful. Looking forward to receiving your valuable feedback.

For any details and clarifications, please contact to:
Mr. Shammi Kapoor at [email protected]

GST Cafe | Services provided by a University, including affiliation of colleges and other allied services given to students, exempt from Service Tax: Madras HC

A single bench of the Hon’ble High Court of Madras in a recent judgment of Madurai Kamraj University vs. Joint Commissioner[1] held that services provided by a University, including affiliation of colleges and other allied services given to students, are exempted from levy of Service Tax as per Finance Act, 1994.

Background:

  • Section 2(a) of the Madurai Kamraj University Act, 1965 (“University Act”) defines an affiliated university as any college affiliated within the area affiliated to university and which conducts the examinations required to be cleared in order to procure the degree of the university. It also includes a college deemed to be affiliated to the University as per the said Act.
  • Section 4(4) and 4(7) of the University Act prescribe the powers of the university to hold examinations and to confer degree, titles, diploma and other academic distinctions; and to affiliate colleges to the university and to withdraw such affiliations respectively.
  • Clause 44 of Section 65-B of the Finance Act, 1994 (“Act”) defines service as any activity carried by one person for another in lieu of consideration. Section 66-B therein prescribes the levy of service tax at the rate of twelve per cent upon the value of the services mentioned in Section 65-B.
  • A list of services exempted from the levy of service tax (“negative list”) has been prescribed under section 66-D of the Act, clause (l) wherein exempts services provided by way of education as part of curriculum for obtaining a qualification recognized by any law for the time being in force.
  • The Central Government had wide powers to exempt any service from the levy of service tax by issuing a notification as per section 93(1) of the Finance Act, 1994. Therefore, some other services were also exempted from the levy of service tax by the Central Government vide a “Mega Exemption Notification”[2], clause 9 wherein was substituted on 11th July, 2014 to exempt the following services:-
    • Services provided by an educational institution to its students, faculty and staff;
    • Services provided to an educational institution, by way of transportation of students, faculty and staff; catering, including any mid-day meals scheme sponsored by the Government, security or cleaning or housekeeping services performed in such educational institution; and
    • Services relating to admission to, or conduct of examination by, such institution;
  • Educational institutions are defined under clause (oa) of the mega exemption notification as institutions providing services as per Section 66-D of the Act. Although this exemption clause (l) of section 66-D of the Act was omitted from 14th May, 2016 onwards, the meaning ascribed to educational institutions under clause (oa) of the mega exemption notification was amplified by way of another notification dated 1st March 2016[3] to include institutions providing education as a part of curriculum for obtaining a qualification recognized by any law for time being in force. Therefore, clause (l) of section 66-D of the Act was operative in essence till a day prior to the inception of Goods and Services Tax, i.e., 30th June, 2017.

Brief Facts of the case:

  • Madurai Kamaraj University (“Petitioner”) has sought for a writ of Certiorari for quashing of the records on the file of the Joint Commissioner GST and Central Excise (“Respondent”) on account of them being illegitimate and arbitrary.
  • The petitioner university was established under the University Act as an affiliating university with the prime function to affiliate the colleges to the university as affiliated, professional or post-graduate colleges and also to withdraw such affiliations.
  • The Petitioner claimed exemption from service tax before the Respondents, for the services rendered by them during the period of 1st April, 2013 to 30th June, 2017, which was rejected by the Respondent, and service tax was demanded from the Petitioner alongwith interest and penalty in a show cause notice dated 23rd October, 2018. The abovementioned demand was confirmed in an order-in-original dated 30th May, 2019, on the ground that exemption clauses are only applicable to institutions imparting education directly and not to the universities providing affiliation to such institutions.
  • Instead of challenging the order before the appellate authorities, the Petitioner has challenged the action of the Respondent of issuing a show cause notice in the Writ Petition as per se

Issue before the Court:

  • whether the services rendered by the petitioner university by granting affiliation and its allied activities and also by providing shelter in their campus to the service providers like Bank, Post Office, or catering etc., directly beneficial to the students, staff and faculty of the university, are exempted services within the meaning of Section 66-D of the Finance Act and also under the Mega Exemption Notification of the year 2012 as amended from time to time.

Observations by the Court:

  • The High Court provided a purposive interpretation and observed that the affiliation activity is an integral part of imparting education for any student for getting qualified to get a qualification like degree or diploma.
  • Accordingly, the services provided by the Petitioner University ie., to give affiliation can be an integral part of the educational services such as admission and examination are being provided jointly, both by the University and the college. The college cannot be said to function independently without the affiliation of the university.
  • Therefore, for the purpose of providing the services of education, both the university as well as the college concerned, who get affiliated to the university, cannot be separated, and are therefore exempted from the levy of Service Tax as per clause 9 of the mega exemption notification.
  • Hence, the court set aside the order in original, thereby exempting the levy of service tax on affiliation services provided by a University.
  • The court further observed that the Petitioner has rightly approached the court by way of a Writ Petition as there was no alternative remedy available to them under section 86 of the Act.

VA Comments:

  • The abovementioned judgment shall have a wide beneficial impact as the Universities are also brought under the ambit of educational institutions for the purpose of providing them an exemption. It is therefore, a welcome move on the part of Universities.

For any further information/ clarification, please feel free to write to:

Mr. Shammi Kapoor, Partner at [email protected]

Mr. Arnab Roy, Principal Associate at [email protected]

Mr. Varenyam Shastri, Associate at [email protected]

…..

[1] WMP (MD) No. 17152 of 2019

[2] Notification No. 25/2012 dated 20th June, 2012

[3] Notification 9/2016 dated 1st March, 2016

Competition News Bulletin – September 2021 – Newsletter

We are glad to share the September 2021 edition of our newsletter – Competition News Bulletin.
Some highlights of this issue are as under:
  • Competition Commission of India (CCI) imposes penalty of INR 200 Crore on Maruti Suzuki Ltd for its discount control policy.
  • CCI directs investigation against Google for alleged abuse of dominant position in the Smart TV market
  • CCI closes case against Uber for alleged abuse of dominant position
  • CCI approves acquisition of 70% equity shareholding in Aakash Education Service Ltd by BYJUS
The Bulletin, now in the 11th year of publication, is amongst India’s first comprehensive Newsletter on the subject published by Vaish Associates Advocates with an aim to supplement CCI’s efforts towards competition advocacy.

For more information please write to Mr. MM Sharma at [email protected]

Between the Lines | Delhi High Court: Arbitral award is liable to be set aside when there is no proper notice of the tribunal’s appointment or of the institution of arbitral proceedings

The Delhi High Court (“DHC”) has in its judgement dated July 15, 2021 in the matter of Komal Narula v. DMI Finance Private Limited and Another [O.M.P. (COMM.) 166/2019 and IA Nos. 6024/2019 & 11657/2020], (“Judgement”) laid down that an arbitral award is liable to be set aside when there is no proper notice of the tribunal’s appointment or of the institution of arbitral proceedings.

Facts

The instant case is an appeal under Section 34 (Application for setting aside arbitral award) of the Arbitration and Conciliation Act, 1996 (“1996 Act”) against an award passed by the arbitral tribunal comprising of a sole arbitrator (“Award”). The impugned Award was rendered in the context of disputes that had arisen between the parties in relation to a common loan agreement dated January 14, 2015 (“Agreement”). DMI Finance Private Limited (“Respondent No. 1”) is registered as a non-banking finance company with the Reserve Bank of India and DMI Housing Finance Private Limited (“Respondent No. 2”) is registered as a housing finance company with the National Housing Bank. Respondent No. 1 and Respondent No. 2 are collectively referred to as “Respondents”. The Respondents are companies of the same group with a common management.

According to the Respondents, Ms. Komal Narula (“Petitioner”), Mr. Nitin Chawla, Mr. Harsh Chawla, Mr. Jitin Chawla and Chawla Iron Traders Private Limited (“Borrower Company”) collectively referred to as “Borrowers”) jointly approached them and requested for financial assistance of INR 1,65,00,000. The Respondents jointly agreed to grant two loans of a sum of INR 1,15,00,000 and INR 50,00,000 respectively (collectively referred to as “Loan Facilities”). The Loan Facilities were sanctioned by the Respondents by letters dated January 14, 2015, which were duly signed by the Borrowers in acceptance of the terms and conditions therein. Subsequently, the parties executed the Agreement, demand promissory note and an affidavit cum undertaking dated January 14, 2015,. In terms of the Agreement and the sanction letter dated January 14, 2015, the Borrowers were liable to pay a sum of INR 2,28,414 per month in 84 (eighty-four) equal monthly instalments (EMI) commencing from March 5, 2015 to Respondent No. 1, towards the repayment of loan, and INR 99,310 per month in 84 (eighty-four) EMI commencing from March 5, 2015 to Respondent No. 2, towards the repayment of loan. The Borrowers, however, failed to make the payments for the aforesaid EMIs regularly. The Respondents, by a letter dated July 16, 2015, recalled the Loan Facilities granted to the Borrowers, alleging that the sale deed documents submitted by the Borrowers were not genuine and, therefore, the Borrowers had “knowingly and wilfully committed fraud and misrepresentation against the lenders”. Accordingly, Respondent No. 1 recalled the amount of INR 1,14,04,541 and Respondent No. 2 recalled the amount of INR 49,58,818 and demanded that the amounts be paid on or before July 23, 2015. However, the Borrowers did not respond to the said letter. Since disputes had arisen between the parties, the Respondents sent a letter dated January 15, 2016, invoking the arbitration clause in the Agreement.

Thereafter, notices dated February 1, 2016 were issued to the Borrowers and Respondents to be present before the arbitrator, but the Borrowers were not represented. The postal report indicated that the Borrowers had refused to accept the notice and the office of the Borrower Company was reported closed, because of which the arbitral tribunal once again issued a notice to the Borrowers, informing the Borrowers that on the further failure to be represented on the fixed date and time, the arbitrator would pass the appropriate order. Such notice was sent to the new address of the Borrowers as well as the old one, and was sent by e-mail too. On March 11, 2016, the Borrowers were represented before the arbitral tribunal by Mr. Gaurav Soni. The arbitral proceedings were thereafter adjourned to March 17, 2016, for which the Borrowers did not appear. By an order dated March 17, 2016, the arbitral tribunal issued a formal notice to the Borrowers and restrained them from creating any third-party interest or alienating, transferring, selling or handing over the possession of the mortgaged property to any third party. The arbitral record indicated that the Borrowers had refused to accept the notices on earlier occasions and that they were served through affixation of the notices at the premises. Thereafter, on March 30, 2016, the learned arbitrator recorded a formal order, to proceed ex parte against the Borrowers. The arbitral tribunal, by the Award, directed that a total amount of INR 1,43,92,456/- was payable to Respondent No. 1 and an amount of INR 62,57,590/- was payable to Respondent No. 2 in respect of their claims. The arbitral tribunal further awarded pendente lite and future interest till realisation of the awarded amounts at the rate of 12% per annum. The arbitral tribunal also awarded costs, which it quantified at INR 80,000/-. Aggrieved by the Award, the Petitioner filed a petition before the DHC, on the ground as set out in Section 34(2)(a)(iii) of the 1996 Act, that the Petitioner was not given a proper notice of appointment of the arbitral tribunal or of the arbitral proceedings and, was unable to defend the case.

Issue

Whether the Petitioner was served due notice of the arbitral proceedings and had full opportunity to defend the case instituted by the Respondents.

Arguments

Contentions raised by the Petitioner:

The Petitioner averred that she had divorced Mr. Nitin Chawla on March 5, 2016 and had been residing separately since January 15, 2014. It was further averred that neither did the Petitioner have anything to do with the Borrower Company nor was she a working director in the Borrower Company and, all debts and liabilities borne by the Borrower Company were required to be discharged by Mr. Nitin Chawla. The Petitioner assailed the Award on the sole ground that the Petitioner did not have any notice of the arbitral proceedings. It was further submitted that the Petitioner did not participate in any business activities of the Borrower Company and was made a director therein merely for registration purposes. Further, due to temperamental differences, she had divorced Mr. Nitin Chawla in the year 2016 and had been assured that she would be removed as a director of the Borrower Company.

The Petitioner argued that the Award was liable to be set aside as no communication was received by the Petitioner from the Respondents. Further, the Respondents were well aware that the Petitioner had divorced Mr. Nitin Chawla and had moved her residence to property bearing no. B-5/12, Paschim Vihar, Delhi- 110063 (“Paschim Vihar Address”). The substitute address of the Petitioner was mentioned in the Agreement and despite knowing the same, the Respondents did not affect service at the said address. It was submitted that neither had the Petitioner received any notice for initiation of arbitral proceedings nor a notice from the arbitral tribunal nor a copy of the ex parte award prior to September 29, 2018 and, therefore, was unable to place her defense. It was also argued that the Petitioner had not authorized Mr. Gaurav Soni to appear on her behalf.

Contentions raised by the Respondents:

It was contended that the Petitioner had signed the power of attorney nominating the Respondents to act, take possession, create mortgage, to register property in the land registry or municipal records along with a letter of continuity, undertaking cum indemnity, along with letter of declaration, letter evidencing deposit of title deeds among other documents. Further, the Petitioner, being a director of the Borrower Company was liable for its acts and omissions. The Award duly recorded deemed service of notice of the arbitration proceedings on the Petitioner. It was further submitted that the notice was sent through e-mail. In addition, dasti (by hand) service was also affected. It was argued that Mr. Gaurav Soni had appeared on behalf of the Petitioner and, on subsequent non-appearance on March 17, 2016, the sole arbitrator proceeded ex parte against the Petitioner. Arguing that the factum of divorce between the Petitioner and Mr. Nitin Chawla was not relevant for the present petition, and referring to master data of the Borrower Company managed by the Ministry of Corporate Affairs, it was submitted that the Petitioner, being the director of the Borrower Company, was actively involved in its affairs.

Observations of the Delhi High Court

The DHC observed that the arbitral tribunal had made a noting that the notice dated February 1, 2016 had been sent to the Petitioner at A-156, Second Floor, Meera Bagh, Delhi – 110087 (“Matrimonial Home”) and her Paschim Vihar Address. The envelope containing the notice sent to her Matrimonial Home bore the noting “refused”. On the basis of the aforesaid the DHC found merit in the Petitioner’s contention that there was no material to indicate that the Petitioner had refused service of the notices at her Paschim Vihar Address. Section 3 (Receipt of written communications) of the 1996 Act provides that notice is deemed to be served “if it is sent to the addressee’s last known place of business, habitual residence or mailing address by registered letter or by any other means which provides a record of the attempt to deliver it”. The DHC noted the postal receipt indicating that the notice was sent by speed post at the Petitioner’s Paschim Vihar Address and, thus, the Petitioner would be deemed to be served at the said address. That being said, the DHC pointed out that it was not established that, in fact, the Petitioner was served the notices or was aware of the proceedings. Considering that the arbitral tribunal had proceeded on the basis that the Petitioner had refused service of the notice, the DHC acknowledged that there was no evidence or any material to indicate that the Petitioner had refused service of the notice sent to her at her Paschim Vihar Address.

Although dasti notices were served on the Borrower Company, the Respondents had not requested for dasti notices to be served on the Petitioner and admittedly, there was no material on record to indicate that the Respondents had personally served any notice to the Petitioner. Considering that the notices served to the Petitioner at her Matrimonial Home had been returned with the noting “refused”, the DHC deemed the assumption made by the learned arbitral tribunal that the Petitioner was duly served as a rebuttable assumption. Noting the matrimonial dispute between the Petitioner and her husband, the DHC observed that the order dated August 18, 2015 passed by the Family Court indicated that the Petitioner had left her Matrimonial Home on January 15, 2014. She had thereafter, been residing at the Paschim Vihar Address. Concededly, the Respondents were aware of the said address.

Considering the circumstances, the DHC opined that it was difficult to accept that the notice dated February 1, 2016 issued by the arbitral tribunal was duly served on the Petitioner at her Matrimonial Home on account of the noting “refused”. The DHC stated that there was ample material on record to indicate that the Petitioner was not residing at the said address on February 1, 2016.

The DHC observed that the arbitral tribunal had proceeded on the basis that since Mr. Gaurav Soni had appeared on behalf of the Borrowers, including the Petitioner, the Petitioner had been duly served the notice regarding the arbitral proceedings and had willfully chosen not to appear before the tribunal. However, Mr. Gaurav Soni did not furnish any authority from the Petitioner to represent her before the arbitral tribunal. The DHC thus affirmed the Petitioner’s claims that she had not authorized Mr. Gaurav Soni or any other person to appear in the arbitral proceedings as she was not aware of the same, and accepted that Mr. Gaurav Soni had not appeared on the instructions of the Petitioner but of her ex-husband.

Decision of the Delhi High Court

The DHC thus held that the Respondents had failed to establish that the Petitioner was duly served the notices regarding constitution of the arbitral tribunal or had due notice of the arbitral proceedings at the material time. The DHC agreed that there was merit in the Petitioner’s contention that she did not have notice of appointment of the arbitral tribunal or of the arbitral proceedings. Hence, the DHC set aside the Award insofar as the Petitioner was concerned, clarifying that the Award is not interfered with in so far as the other Borrowers are concerned. The DHC further clarified that the Respondents were at liberty to institute fresh proceedings against the Petitioner.

VA View:

The DHC has through this Judgement clarified that an arbitral award can be set aside, if notice of initiation of arbitral proceedings is not duly served to any of the parties to the dispute, with regards to that party. The DHC has upheld the rationale behind sending notice of institution of arbitral tribunal and initiation of arbitral proceedings, that is, the parties to the dispute against whom a claim is made should know what the claims are. In response to such notice, the recipient of the notice may accept the claims either wholly or partially.

Service of notice is crucial for the parties to understand the claims against them and to analyze whether the claims are tenable in light of the factual matrix of the dispute, thereby allowing them to defend themselves. Thus, not serving a notice to any of the parties to the dispute takes away a full opportunity to defend the case instituted. Hence, the DHC has rightly established that improper service of notice can consequently result in the arbitral award being set aside qua such party.

For more information please write to Mr. Bomi Daruwala at [email protected]